Creating a Schedule or Quantity
Click Manage tab
Views panel
Schedules drop-down
Schedule/Quantities.
In the New Schedule dialog, select a component from the category list. A default name appears in the Name text box, which you can change as necessary.
Select Schedule building components.
Note:
Do not select Schedule keys. If you want to create a key schedule, see
http://beehive.autodesk.com/community/service/rest/cloudhelp/resource/cloudhelpchannel/guidcrossbook/jsonp?v=B3&p=VASARI&l=ENU&guid=GUID-CD22DA24-4162-4AB2-B1D3-02CEBE918444
.
Specify the phase.
Click OK.
In the Schedule Properties dialog, specify the schedule properties. See
Specifying Schedule Properties
.
Click OK.
Related topics
Modifying Schedules
Parent topic: