To set or modify the task type
The task type defines how the items attached to the task will be displayed during simulation. For example, a default construction sequence would start with all items hidden, as the task starts the attached items will be displayed in transparent green, then as the task ends the attached items will be displayed as they are in the normal model display (this may be with materials applied if previously set up in the Presenter tool). Task types themselves can be defined and new types created on the Configure Tab.