Revision tracking is the process of recording changes made to a building model after sheets have been issued. In Revit, you display and track revisions using revision clouds, tags, and schedules.
Typically you manage the revision process as follows:
- Enter information about the revision in the Sheet Issues/Revisions dialog.
See Entering Revision Information.
- Update the Revit project to implement the change.
- In one or more project views, draw revision clouds to indicate the areas that changed.
See Adding a Revision Cloud.
- Assign a revision to each cloud.
See Assigning a Revision to a Revision Cloud.
- Tag the revision clouds to identify the assigned revisions.
See Tagging a Revision Cloud.
- Check sheets to make sure that the revision schedules show the desired information.
See Specifying the Revisions to Include in a Revision Schedule.
- Issue the revisions.
See Issuing a Revision.