When a concept is ready, you can switch to the Revit project environment. For example, you may want to perform area analyses, evaluate floors, or add curtain walls. Then, if the evaluation indicates that you need more floor area on a level, you can move the design back into the conceptual design environment to make the adjustment.
The following procedures define:
- how to move a massing family between the conceptual design and project environments, and how to edit it in the conceptual design environment.
- how to move an in-place massing family between the conceptual design and project environments, and how to edit it in the conceptual design environment.
Tip: An easy way to switch views is to click
Recent Documents, and select one of the views you have used.