In this exercise, you will review the options that are available for quantity takeoff criteria and reports.
The quantity takeoff report settings include the default quantity takeoff criteria used to create material lists and default styles for tables. The quantity takeoff criteria includes a list of materials that specifies the surfaces and shapes from which you want to generate volume information.
Review quantity takeoff settings
The drawing opens, displaying three viewports.
Examine the quantity takeoff criteria
Three styles are defined in the collection.
This tab contains a pre-defined table for calculating earthworks (cut and fill) by comparing a Datum surface layer to an existing ground surface layer.
You will use the Earthworks criteria in the next exercise to calculate the quantity takeoff.
Notice that the Condition for the EG surface is set to Base, while the condition of the Datum surface is set to Compare. This indicates that the material is going to be fill when Datum is above EG, and cut when Datum is below EG.
Also note the three Factor values in the table:
To continue this tutorial, go to Exercise 2: Creating a Material List.