Site Analysis Phase Workflow

In the first phase of a project, a preliminary analysis of a site is necessary to determine if the project is feasible.

As an example of this phase, a survey crew would go to the site with a mapping grade GPS data collector to map wetlands that have been delineated on the site. This information is imported into a survey network of the project's survey database and overlaid onto a map of the area along with other relevant information, such as a steep slope analysis of the site’s topography.

To accomplish this phase in AutoCAD Civil 3D:

Create a new project In Toolspace on the Prospector tab choose Master View and create a new project or create a local survey database.
Check out the Survey Database If you are working with the project management tools, open the Survey database for editing and import the wetland mapping points and line features.
Create a new survey network Create a network with a relevant name to the site (<name>_Site Analysis) and import the points and line work into the survey database.