** ERROR 220021 ** Velocity/pressure switch-over time cannot be after injection time.
The velocity (filling) control phase has been specified by an injection time, however the switch-over from velocity to pressure control (packing) has been specified by a time value which is greater than the injection time. Therefore, switch-over to pressure control cannot occur before the cavity is 100% filled.
Select Velocity/pressure switch-over time, or under Filling control, set a longer injection time.
and set an earlier