Migrate Linked Models

If you are migrating an existing project into Collaboration for Revit, there are likely links between your project models that need to be migrated. Use this procedure to migrate linked models for a Revit project for collaboration on A360.

When you initiate A360 collaboration from Revit on a model that includes Revit links, you also need to migrate the linked models. Initiate A360 collaboration from Revit on each of the linked models, and then use the Manage Links tool to reload the links from their cloud location.

  1. Open the linked model in Revit.
  2. Click Collaborate tabManage Collaboration panel (Collaborate).
  3. Select the A360 project where the host Revit model is stored, and click OK.
  4. In the Collaboration Using A360 dialog, click Initiate.

    Revit displays information about the status of the initiation process.

  5. Click Close to continue.
  6. Repeat the above process for each linked Revit model.
  7. After you have initiated A360 collaboration from Revit on all linked models, open the host model in Revit.
  8. Click Manage TabManage Project panel (Manage Links).
  9. On the Revit tab of the Manage Links dialog, select a linked model, and click Reload From.

    Notice that the file browser opens by default to the A360 project location.

  10. Select the name of the linked file, and click Open.

    The cloud version of the link will be locally-cached on your machine and loaded.

  11. Repeat the previous 2 steps to reload each linked model from the cloud location.
  12. Click OK to close the Manage Links dialog.
Note: When an A360 project is renamed, the Manage Links dialog may still reference the old project name in the link paths. The links will still resolve correctly, however the path may be confusing. Use the Synchronize with Central command to update the Saved Path to the new project name, and then click Reload to update the link paths in the Manage Links dialog.