When Should I Use Copy/Monitor?

Use the Copy/Monitor tool when

Sample workflows:

  1. The architect designs the architectural model.
  2. The structural engineer creates an empty structural project and uses Copy/Monitor to copy levels and grids from the linked architectural model, providing a starting point for the structural design.
    1. The architect links the structural model into the architectural project to monitor levels and grids.
    2. Whenever the architect or structural engineer moves or changes a level or grid, the other team member is notified of the change.
  3. The mechanical engineer creates an empty mechanical project and uses Copy/Monitor to copy levels from the linked architectural model, providing a starting point for the mechanical design.
    1. Whenever the architect moves or changes a level, the mechanical engineer is notified of the change.