Cost Adviser dialog-Molding Cost page

Specify the running costs for the injection molding machine, and the historical downtime.

The production cost to manufacture the part is incorporated into the Cost Adviser. The Cycle time can be adjusted if required (operator cycle time longer than machine cycle time for example) by checking the Override calculated cycle time box and entering the required cycle time.

Color changes will effect the setup cost. Ensure different colored parts produced in the same run carry their portion of the mold change cost.

The Machine cost is the hourly rate charged for the molding machine. The labor required to run the molding machine should be included in this figure. If post molding operations are included within the cycle time, you will need to decide how you will allocate the labor component

Historical figures can assist in setting the Downtime expected for this part.

Dialog elements

Molding Cost
Displays information relating to the machine costs of part production.
Override calculated cycle time
Allows manual specification of the cycle time.
Cycle time
Displays the cycle time for the part.
Note: When the Cycle Time is determined by Autodesk Moldflow Adviser, its value may vary from the actual cycle time due to the number of variables upon which cycle time depends. A longer actual cycle time will result in a higher part cost because of increased power requirements for the molding machine and a longer overall production run.

Select the Override calculated time option in the Cost Adviser dialog to change the automatically calculated cycle time.

Running cost per shot
The cost to set up the molding machine for the production run.
Machine cost
The running costs associated with producing shots during one, or several hours.
Downtime
Specify the amount of time the machine will be offline for fitting, maintenance, repair, or other reasons, as a percentage of the entire production run.
Estimated Molding Cost
Displays the estimated molding cost, based on the running costs.
Molding cost per shot
Displays the molding cost for total production, including the setup and machine costs.
The Cost Adviser also takes into account the cycle time, and the downtime percentage.
Molding cost for total production
Displays the molding cost for total production, including the setup and machine costs.
The Cost Adviser also takes into account the cycle time, and the downtime percentage.