Prerequisities
- A model includes a cooling circuit.
- An analysis sequence set for the model includes Cool (FEM)
- Mold temperature option is set to
Transient within cycle or
Transient from production start-up.
- Click
Coolant Inlets / Outlets () and select
Thermocouple Controlled Inlets.
In the Set Thermocouple controlled cooling inlet dialog opens.
- In the dialog, click
New to specify an inlet.
The Thermocouple Controlled Cooling Inlet dialog opens.
- In the dialog, on the Thermocouple Controlled Cooling Control tab, specify a name of the inlet, coolant, and valve control method.
- On the Valve On and Valve Off tabs, and specify a coolant control method, flow rate, and coolant inlet temperature. Click
OK.
- Click on a model where you wish to create the thermocouple controlled cooling inlet.
The thermocouple controlled cooling inlet is created.