Best Practices: Managing a Team Project

When setting up or managing a team project, consider these recommendations.

Verify Software Build

Verify that the same Revit build is installed on all computers that share worksets.

Specify a Starting View

You can specify the default view that is opened when the central or any local model is opened. Use a simple view where you post project information or notices to share with team members whenever they open the model.

Fix Posted Warnings

Use the Select Link command to identify and fix posted warnings prior to allowing local copies. Click Collaborate tabCoordinate panelCoordination Review drop-downSelect Link.

Use Audit

Periodically open the central model with the Audit option selected and then save the model. If corrupted elements are encountered during the audit, they are deleted if possible and the user is notified.

Backups

Ensure that a sufficient number of backups are being created. At a minimum, you should have at least one backup for each member of your worksharing team in order to increase the likelihood that each team member's data is saved as part of the backups.

Note: Backups are not supported for the server-based worksharing workflow.