Saving or closing your drawing will sync it with the project by default (this can be changed in settings). To manually sync your current/active drawing changes, use the Check In ribbon button.
- With your Collaboration project open, click the Collaboration tab
Check In
.
The Check In dialog is displayed.
- If you want to check in the changes to your drawing and keep it open for further changes, select Keep files open for editing after check out.
- If you want to remove your locally cached files, select Cleanup cached files.
- Type any comments you want associated with this version of the file in the Comments to include with this version section.
- Click OK.
Note: To sync changes from more than one drawing, select a node in the Project Manager, right-click and click Check In. All the items in the tree in that location go through the check in process.