To Move Circuits to Manage Demand Load

When you view circuits in the Circuit Manager and see that the load is too high on a panel, move one or more of its circuits to a different panel. All of the information about the circuit and its device connections moves with the circuit to the new panel.

Unless you have used wire to represent the circuit, you can make this move without physically changing anything in your drawing. If you are using an electrical project database, you are prompted to open and save any linked drawings that are affected by the modifications.

To move circuits between panels

  1. In the Electrical workspace, select a panel and click Panel tab Circuits panel Circuit Manager .
  2. In the Circuit Manager, in the expanded panel tree view in the left pane, click the circuit to be moved and drag it onto a different panel.

    You can now see the voltage and load information change in the Circuit Manager.

    Note: Anytime you modify circuits, you will need to update any existing panel schedules. See Updating Panel Schedules