To Use Calculation Projects

You import all observations that shall be processed in one adjustment process into one calculation project. You can combine multiple measurements and measurements from different instruments in one calculation project.

To start the Project Manager

  1. In the AutoCAD Map 3D toolset Maintenance workspace, do one of the following:

    Click Insert tab > Survey panel > Survey.

  2. Click Project Manage.
  3. In the Manage Projects dialog box, select a project group and a project, and edit the calculation project.

Calculation Project option

Description

Calculation Project area

Provides tools to manage calculation projects. Click to display all options.

Select A Calculation Project

Selects a calculation project.

Create

Creates a calculation project. Enter name and description.

Delete

Deletes the selected calculation project.

Edit

Edits the calculation project name and description.

Copy

Copies the calculation project. For example, use this function to create a backup of a particular calculation stage such as a adjustment calculation without detail points.