To Attach Tasks to a Current Selection

To attach tasks to a current selection

  1. If the TimeLiner window is not already open, click Home tab Tools panel TimeLiner.
  2. Select the desired geometry objects in the Scene View, or on the Selection Tree.
  3. In the TimeLiner window Tasks tab, hold the CTRL or SHIFT key to select all required tasks.
  4. Right-click the task selection, and click Attach Current Selection. Alternatively, click Attach Attach Current Selection on the Tasks tab.
Tip: If you need to add additional items to already attached tasks, click Attach Append Current Selection, otherwise any previous task attachments will be overridden. If you made a mistake, select the task and click Clear Attachment .