To Add Tasks Based on the Selection Tree Structure

To add tasks based on the Selection Tree structure

  1. If the TimeLiner window is not already open, click Home tab Tools panel TimeLiner.
  2. In the TimeLiner window Tasks tab, click Auto-Add Tasks .
  3. Click For Every Topmost Layer if you want to create tasks with the same names as each topmost layer in the Selection Tree.

    Click For Every Topmost Item if you want to create tasks with the same names as each topmost item in the Selection Tree. This can be a layer, a group, block or cell, or geometry, depending on how the model is constructed.

Note: Planned Start and End dates will be automatically created, starting from the current system date and incrementing by one day for each subsequent end and start date. The Task Type will be set to Construct.