To Refresh Tasks to Reflect Project Changes

To refresh tasks to reflect project changes

  1. Make changes to the project in the scheduling software, and save it.
  2. Load your model into Autodesk Navisworks (see Open Files if you need help).
  3. Click Home tab Tools panel TimeLiner , and click the Data Sources tab in the TimeLiner window.
  4. Click the Refresh button and select Selected Data Sources or All Data Sources.
  5. In the Refresh from Data Source Dialog Box select one of the following options and click OK.
    • Rebuild Task Hierarchy. Choose this to re-import all tasks and associated data from the selected project file(s), and rebuild the task hierarchy on the Tasks tab.
    • Synchronize. Choose this to update all existing tasks in the Tasks tab, with the latest associated data from the selected project file(s) (for example, Start and End dates).
  6. Tip: You can also right-click data source in the Data Sources tab and select the Synchronize or Rebuild Task Hierarchy option.