To Move Tasks Up and Down the Task Hierarchy

To move tasks up and down the task hierarchy

  1. If the TimeLiner window is not already open, click Home tab Tools panel TimeLiner.
  2. In the TimeLiner window Task tab, click the tasks you want to move:
    • Click Move Up to move selected tasks up one place the task hierarchy
    • Click Move Down to move selected tasks down one place the task hierarchy
    Note: Tasks can only move within their current level of hierarchy. If the selected tasks are within a summary task, then they can only be moved up or down within the summary task.