Space Type Data for Energy Analysis

Learn about the default settings for space types in Revit.

You can change the default values for space type parameters. See Space Properties.

Active Storage

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Warehouse 7 am - 4 pm
People/100 sq. M. 3.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.8
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Active Storage - Hospital/healthcare

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 3.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.9
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Air/Train/Bus - Baggage Area

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 100.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Airport Concourse

Parameter Default Value
Occupancy Schedule Large Assembly Hall 8 am - 10 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 100
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.6
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Atrium - Each additional floor

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 33.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.2
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Atrium - First 3 floors

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 33.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.6
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Audience/Seating Area - Penitentiary

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 150
People Sensible Heat Gain (Btu/hr) 225
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 0.7
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Audience/Seating Area - Exercise Center

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 150
People Sensible Heat Gain (Btu/hr) 225
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 0.3
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Audience/Seating Area - Gymnasium

Parameter Default Value
Occupancy Schedule Common Commercial 7 am - 6 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 150
People Sensible Heat Gain (Btu/hr) 225
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 0.4
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Audience/Seating Area - Sports Arena

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 150
People Sensible Heat Gain (Btu/hr) 225
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 0.4
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Audience/Seating Area - Convention Center

Parameter Default Value
Occupancy Schedule Large Assembly Hall 8 am - 10 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 150
People Sensible Heat Gain (Btu/hr) 225
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 0.7
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Audience/Seating Area - Motion Picture Theatre

Parameter Default Value
Occupancy Schedule Large Assembly Hall 8 am - 10 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 150
People Sensible Heat Gain (Btu/hr) 225
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 1.2
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Audience/Seating Area - Performing Arts Theatre

Parameter Default Value
Occupancy Schedule Large Assembly Hall 8 am - 10 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 150
People Sensible Heat Gain (Btu/hr) 225
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 2.6
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Audience/Seating Area - Religious

Parameter Default Value
Occupancy Schedule Large Assembly Hall 8 am - 10 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 120
People Sensible Heat Gain (Btu/hr) 225
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 1.7
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Audience/Seating Area - Police/Fire Station

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 50.0
People Sensible Heat Gain (Btu/hr) 225
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 0.93
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Audience/Seating Area - Courthouse

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 70.0
People Sensible Heat Gain (Btu/hr) 225
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 0.93
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Audience/Seating Area - Auditorium

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 150
People Sensible Heat Gain (Btu/hr) 225
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 0.93
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Bank Customer Area

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 30.0
People Sensible Heat Gain (Btu/hr) 225
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 1.49
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Banking Activity Area - Office

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 5.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.5
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.3
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Barber and Beauty Parlor

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 25.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1
Power Load Density (W/sq. ft.) 2
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Card File and Cataloguing - Library

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.1
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Classroom/Lecture/Training - Penitentiary

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 65.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.3
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Classroom/Lecture/Training

Parameter Default Value
Occupancy Schedule School 8 am - 9 pm
Power Schedule School 7 am - 9 pm
People/100 sq. M. 65.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.4
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Confinement Cells - Penitentiary

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 25.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.93
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Confinement Cells - Court House

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 25.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.9
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Conference/Meeting/Multipurpose

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 50.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.3
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Corridor/Transition

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.5
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Corridor/Transition - Manufacturing Facility

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 00.5
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Corridor w/Patient Waiting Exam - Hospital/Healthcare

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Court Sports Area - Sports Area

Parameter Default Value
Occupancy Schedule Large Assembly Hall 8 am - 10 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 30.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 2.3
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Courtroom - Court House

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 70.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 2.3
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Department Store Sales - Retail

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 15.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 2.14
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Detailed - Manufacturing Facility

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 2.1
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Dining Area

Parameter Default Value
Occupancy Schedule Restaurant Lunch and Dinner
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 70.0
People Sensible Heat Gain (Btu/hr) 275
People Latent Heat Gain (Btu/hr) 275
Lighting Load Density (W/sq. ft.) 0.9
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Dining Area - Hotel

Parameter Default Value
Occupancy Schedule Restaurant Lunch and Dinner
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 70.0
People Sensible Heat Gain (Btu/hr) 275
People Latent Heat Gain (Btu/hr) 275
Lighting Load Density (W/sq. ft.) 1.3
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Dining Area - Family Dining

Parameter Default Value
Occupancy Schedule Restaurant Lunch and Dinner
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 70.0
People Sensible Heat Gain (Btu/hr) 275
People Latent Heat Gain (Btu/hr) 275
Lighting Load Density (W/sq. ft.) 2.1
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Dining Area - Lounge/Leisure Dining

Parameter Default Value
Occupancy Schedule Restaurant Lunch and Dinner
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 70.0
People Sensible Heat Gain (Btu/hr) 275
People Latent Heat Gain (Btu/hr) 275
Lighting Load Density (W/sq. ft.) 1.4
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Dining Area - Motel

Parameter Default Value
Occupancy Schedule Hotel 24 hrs
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 70.0
People Sensible Heat Gain (Btu/hr) 275
People Latent Heat Gain (Btu/hr) 275
Lighting Load Density (W/sq. ft.) 1.2
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Dining Area - Transportation

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 100.0
People Sensible Heat Gain (Btu/hr) 275
People Latent Heat Gain (Btu/hr) 275
Lighting Load Density (W/sq. ft.) 0.93
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Dining Area - Penitentiary

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 100.0
People Sensible Heat Gain (Btu/hr) 275
People Latent Heat Gain (Btu/hr) 275
Lighting Load Density (W/sq. ft.) 1.3
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Dining Area - Civil Services

Parameter Default Value
Occupancy Schedule Restaurant Lunch and Dinner
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 100.0
People Sensible Heat Gain (Btu/hr) 275
People Latent Heat Gain (Btu/hr) 275
Lighting Load Density (W/sq. ft.) 0.93
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Dormitory Bedroom

Parameter Default Value
Occupancy Schedule Home 24 hrs
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 155
Lighting Load Density (W/sq. ft.) 1.11
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Dormitory Study Hall

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 155
Lighting Load Density (W/sq. ft.) 1.11
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Dressing/Locker/Fitting Room - Gymnasium

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 20.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.6
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Dressing/Locker/Fitting Room - Court House

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Lighting Schedule Office Lighting 6 am - 11 pm
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.56
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Dressing/Locker/Fitting Room - Performing Arts Theatre

Parameter Default Value
Occupancy Schedule Large Assembly Hall 8 am - 10 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 20.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.56
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Dressing/Locker/Fitting Room - Auditorium

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 20.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.56
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Dressing/Locker/Fitting Room - Exercise Center

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 20.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.56
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Electrical/Mechanical

Parameter Default Value
Occupancy Schedule Restaurant Lunch and Dinner
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 3.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.5
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Elevator Lobbies

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.3
Power Load Density (W/sq. ft.) 0.2
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Emergency - Hospital/Healthcare

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 2.7
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Equipment Room - Manufacturing Facility

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 3.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.2
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Exam/Treatment - Hospital/Healthcare

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 20.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.5
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Exercise Area - Exercise Center

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 30.0
People Sensible Heat Gain (Btu/hr) 710
People Latent Heat Gain (Btu/hr) 1090
Lighting Load Density (W/sq. ft.) 0.93
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Exercise Area - Gymnasium

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 30.0
People Sensible Heat Gain (Btu/hr) 710
People Latent Heat Gain (Btu/hr) 1090
Lighting Load Density (W/sq. ft.) 0.9
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Exhibit Space - Convention Center

Parameter Default Value
Occupancy Schedule Large Assembly Hall 8 am - 10 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 50.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.3
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Fellowship Hall - Religious Buildings

Parameter Default Value
Occupancy Schedule Large Assembly Hall 8 am - 10 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 120.0
People Sensible Heat Gain (Btu/hr) 225
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 0.9
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Fine Material - Warehouse

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Warehouse 7 am - 4 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.4
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Fine Merchandise - Sales Area Retail

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 15.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 2.14
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Fire Station Engine Room - Police Fire Station

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.8
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Food Preparation

Parameter Default Value
Occupancy Schedule Restaurant Lunch and Dinner
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 20.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.2
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Garage Service/Repair - Automotive Facility

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.7
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

General High Bay - Manufacturing Facility

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.7
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

General Low Bay - Manufacturing Facility

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.2
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

General Exhibition - Museum

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 40.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Hospital - Nursery - Hospital/Healthcare

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.6
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Hospital - Medical Supplies - Hospital/Healthcare

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 3.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.4
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Hospital/Radiology- Hospital/Healthcare

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 20.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.4
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Hotel/Conference Center - Conference/Meeting

Parameter Default Value
Occupancy Schedule Hotel 24 hrs
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 50.0
People Sensible Heat Gain (Btu/hr) 225
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 1.3
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Inactive Storage

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Warehouse 7 am - 4 pm
People/100 sq. M. 3.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.3
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Judges Chambers - Court House

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 50.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.3
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Laboratory - Office

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 5.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.4
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Laundry - Ironing and Sorting

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 20.0
People Sensible Heat Gain (Btu/hr) 275
People Latent Heat Gain (Btu/hr) 475
Lighting Load Density (W/sq. ft.) 0.56
Power Load Density (W/sq. ft.) 3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Laundry - Washing - Hospital/Healthcare

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 275
People Latent Heat Gain (Btu/hr) 475
Lighting Load Density (W/sq. ft.) 0.6
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Library - Audio Visual - Library - Audio Visual

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 25.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.3
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Living Quarters - Dormitory

Parameter Default Value
Occupancy Schedule Hotel 24 hrs
Power Schedule Residential Lighting All Day
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 155
Lighting Load Density (W/sq. ft.) 1.1
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Living Quarters - Motel

Parameter Default Value
Occupancy Schedule Hotel 24 hrs
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 155
Lighting Load Density (W/sq. ft.) 1.11
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Living Quarters - Hotel

Parameter Default Value
Occupancy Schedule Hotel 24 hrs
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 155
Lighting Load Density (W/sq. ft.) 1.1
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Lobby

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 150.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 155
Lighting Load Density (W/sq. ft.) 1.3
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Lobby - Religious Building

Parameter Default Value
Occupancy Schedule Large Assembly Hall 8 am - 10 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 150.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.3
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Lobby - Motion Picture Theatre

Parameter Default Value
Occupancy Schedule Large Assembly Hall 8 am - 10 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 150.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.1
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Lobby - Auditorium

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 150.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.3
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Lobby - Performing Arts Theatre

Parameter Default Value
Occupancy Schedule Large Assembly Hall 8 am - 10 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 150.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 3.3
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Lobby - Post Office

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 150.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.3
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Lobby - Hotel

Parameter Default Value
Occupancy Schedule Hotel 24 hrs
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 150.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.1
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Lounge or Recreation

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 30.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.21
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Mail Concourse Sales Area - Retail

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 40.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.7
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Mass Merchandising Sales Area - Retail

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Warehouse 7 am - 4 pm
People/100 sq. M. 15.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.11
Power Load Density (W/sq. ft.) 0.1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Medium/Bulky Material - Warehouse

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Warehouse 7 am - 4 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.9
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Merchandising Sales Area - Retail

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 15.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 2.14
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Museum and Gallery - Storage

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 5.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.84
Power Load Density (W/sq. ft.) 0.2
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Nurse Station - Hospital/Healthcare

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.3
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Office - Enclosed

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 5.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.3
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Office - Open Plan

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 5.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.1
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.3
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Office - Common Activity Areas - Inactive Storage

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Warehouse 7 am - 4 pm
People/100 sq. M. 3.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.28
Power Load Density (W/sq. ft.) 0.2
Electrical Equipment Radiant Percentage 0.3
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Operating Room - Hospital/Healthcare

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 20.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 2.2
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Other Televised Playing Area - Sports Arena

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 150.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.4
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Parking Area - Attendant Only - Parking Garage

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 5.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.19
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Parking Area - Pedestrian - Parking Garage

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 5.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.2
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Patient Room - Hospital/Healthcare

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.7
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Personal Services Sales Area - Retail

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 15.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 2.14
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Pharmacy - Hospital/Healthcare

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.2
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Physical Therapy - Hospital/Healthcare

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 20.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.9
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Playing Area Gymnasium

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 30.0
People Sensible Heat Gain (Btu/hr) 710
People Latent Heat Gain (Btu/hr) 1090
Lighting Load Density (W/sq. ft.) 1.4
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Plenum

Parameter Default Value
Occupancy Schedule Cooling/Heating Off 24 hrs
Power Schedule Cooling/Heating Off 24 hrs
People/100 sq. M. 00
People Sensible Heat Gain (Btu/hr) 0
People Latent Heat Gain (Btu/hr) 0
Lighting Load Density (W/sq. ft.) 0
Power Load Density (W/sq. ft.) 0
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0
Carpet (Y/N) N

Police Station Laboratory - Police/Fire Stations

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 25.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.39
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Public and Staff Lounge - Hospital/Healthcare

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 25.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.84
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Reading Area - Library

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.2
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Reception/Waiting - Transportation

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 100.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.1
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Reception/Waiting - Motel

Parameter Default Value
Occupancy Schedule Hotel 24 hrs
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 30.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.1
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Reception/Waiting - Hotel

Parameter Default Value
Occupancy Schedule Hotel 24 hrs
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 30.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.1
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Recovery - Hospital/Healthcare

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 20.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.8
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Restoration - Museum

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 40.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.7
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Restrooms

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.9
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Ring Sports Area - Sports Arena

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 70.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 2.7
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Sleeping Quarters - Police/Fire Station

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 20.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 105
Lighting Load Density (W/sq. ft.) 0.3
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Sorting Area - Post Office

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 5.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.2
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Specialty Store Sales Area - Retail

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 15.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 2.14
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Stacks - Library

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.7
Power Load Density (W/sq. ft.) 1.5
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Stairs - Inactive

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.56
Power Load Density (W/sq. ft.) 0.2
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Stairway

Parameter Default Value
Occupancy Schedule Common Office 8 am - 5 pm
Power Schedule Office Lighting 6 am - 11 pm
People/100 sq. M. 10.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 0.6
Power Load Density (W/sq. ft.) 0.3
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Supermarket Sales Area - Retail

Parameter Default Value
Occupancy Schedule Retail Facility 7 am - 8 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 8.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 2.1
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Terminal - Ticket Counter - Transportation

Parameter Default Value
Occupancy Schedule Healthcare Facility 8 am - 9 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 100.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.5
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y

Workshop - Workshop

Parameter Default Value
Occupancy Schedule Warehouse 7 am - 4 pm
Power Schedule Warehouse 7 am - 4 pm
People/100 sq. M. 20.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 1.9
Power Load Density (W/sq. ft.) 1
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) N

Worship - Pulpit Choir - Religious

Parameter Default Value
Occupancy Schedule Large Assembly Hall 8 am - 10 pm
Power Schedule Retail Lighting 7 am - 8 pm
People/100 sq. M. 120.0
People Sensible Heat Gain (Btu/hr) 250
People Latent Heat Gain (Btu/hr) 200
Lighting Load Density (W/sq. ft.) 2.4
Power Load Density (W/sq. ft.) 0.54
Electrical Equipment Radiant Percentage 0.5
Infiltration Flow (CFM/sq. ft.) 0.038
Carpet (Y/N) Y