Specify a Schedule Mark

You assign rebar schedule marks to rebar and rebar couplers for the scheduling and organization of logically grouped reinforcement.

Enter or add a schedule mark to rebar or rebar couplers

  1. Select all rebar instances, rebar sets, or couplers to be marked. To select multiple instances, hold down the CTRL key while selecting.
  2. On the Properties palette, find the Schedule Mark parameter in the Construction section. Enter a new schedule mark or select a mark from the drop-down.
    Note: New schedule marks are available for all rebar instances in the project.

Selecting all rebar with similar schedule marks

  1. Right click a rebar instance.
  2. Click Select Rebar by Schedule Mark from the drop-down list.

    Group the selection or mass edit using the Properties palette.

    Note: By default, the lowest numerical schedule mark available is assigned to the rebar. Typically, this mark is 1, though modified projects can be different.