Copy a Revision Scheme Format to Apply to Another Revision Scheme
Copy an existing revision scheme format to apply to a current revision scheme.
Click Tools Administration Vault Settings.
On the Vault Settings dialog box, select the Behaviors tab Revisions.
Select a revision scheme for which you want to create a new format, and click Edit.
Click the Scheme Format tab, select the scheme format to copy, and then click Copy.
In the List Scheme Format dialog box, the default name Copy of <original scheme name> appears in The Scheme format Name box. Change the name by replacing it with a name you enter.
Re-prioritize values by selecting a value and clicking the move up arrow or move down arrow.
Select a value that is not checked to assign it as the default, and then click Set as Default.
Add a new row by clicking Add, and then enter the value in the List Values list.