Change the Task Costs
Note: By default only the Total Cost is shown in the Tasks tab. To show all task costs click Column Set > Extended or select columns from the
Choose TimeLiner Columns dialog box.
In the TimeLiner window > Tasks tab, click the task cost that you want to modify.
Note: The Total Cost is the sum of the other costs assigned to a task, and cannot be modified. Costs cannot be added to summary tasks. The summary task costs are the sum of the costs of its child tasks.
Type in the cost and press Enter.
Note: You can enter an unlimited number of decimal places but in the display they will be rounded to two decimal places. The underlying value is used during cost calculations.