Include Elements from Linked Models in a Schedule

  1. Open the schedule in the host project.
  2. On the Properties palette, for Fields, click Edit.
  3. Select Include elements in links.

    Information about model elements in linked models is now available to the schedule.

  4. To include project information from a linked model, for Select Available Fields From, select Project Information. Add the desired fields from the Available Fields list to the Scheduled Fields list.
  5. To include the linked model instance name or file name, for Select Available Fields From, select RVT Links. Add the desired fields from the Available Fields list to the Scheduled Fields list.
    Note: In the schedule, the file name does not include the file path or the file extension. In addition, if there are visible nested links in a linked model, the file name that displays for elements in the nested link is the parent link.
  6. Click OK.

Now you can specify which linked models should be visible in the schedule.