When Slopes is selected in the left panel, the right panel displays a table of slope values available in a project. 
 Slope values can be copied to another project using the Transfer Project Standards feature. 
Adding a Slope Value
- Click 
 New Slope.  
- In the New Slope dialog, enter a slope value. 
 If the slope value entered is greater than 45 degrees, a warning displays. 
  
- Click OK. 
 
 
Deleting a Slope Value
- Select a slope in the Slope Values list. 
 
- Click 
 Delete Slope. The slope value is removed from the project. 
Note: The default 0 (zero) slope value cannot be deleted. 
  
  
- Click Yes.