Copy an existing revision scheme format to apply to a current revision scheme.
- Click Tools > Administration > Vault Settings.
- In the Vault Settings dialog, select the
Behaviors
tab > Revisions.
- Select a revision scheme for which you want to create a new format, and click Edit.
- Click the Scheme Format tab, select the scheme format to copy, and then click Copy.
- In the List Scheme Format dialog, the default name Copy of <original scheme name> appears in The Scheme format Name box. Change the name by replacing it with a name you enter.
- Re-prioritize values by selecting a value and clicking the
move up
arrow or
move down arrow.
- Select a value that is not checked to assign it as the default, and then click
Set as Default.
- Add a new row by clicking Add, and then enter the value in the List Values list.
- Select a value to remove, and then click Remove.
- Click OK.