To Relink Pressure Networks to Their Paths

Path-based pressure networks can occasionally become detached from their underlying alignments when you are editing them. Use the Relink Pipe Run command to relink the parts to the underlying pipe run alignment.

Select the parts you want to relink and then select the alignment you want to link to.

Note: You can use the DetachPipeRun command to manually detach a pressure network pipe run from its path if needed.
  1. Select the pipe run that you want to relink.
  2. On the contextual ribbon, click Modify panel Relink Pipe Run .
    Note: This command is also accessible from the Pipe Runs node in the Prospector tree for an existing pressure network.
  3. Select the first pressure network part to relink.
  4. Select the next pressure network part to relink.
    Note: You can select the first and last part to relink, and the entire pipe run will be selected.
  5. Press Enter to complete the selection.
  6. Select the alignment to relink the pipe parts to.