To Update Drawings From the Project Database

Import changes made to the project database back to the drawings and update components.

  1. Copy the project database file to a new name.
  2. Using Access, edit the component or drawing values within the tables that can be imported and save the database file.
  3. Click Import/Export Data tabImport panel From Project MDB. Find
  4. Select the database file.
  5. Select the tables for import.
  6. Select whether to force the values to upper case or to use the values as entered in the database.
    Note: If the environment file (wd.env) has setting SETQ:GBL_wd_importdbUppercase,0 then the Force values to upper case is unchecked initially.
  7. Select the drawings to process.