To Change the Elevation of a Cable Tray or Conduit Run

To manage changes to cable tray or conduit when elevation changes

  1. Select the segment you want to modify.
  2. Specify a defined elevation or enter a new value in the following locations:
    • For cable tray, click Cable Tray tab Modify panel Modify Cable Tray in the Modify Cable tray dialog box
    • For conduit, on the Properties palette, under Placement

      You can also modify conduit location coordinates, elevation values, and connection types for all conduit connectors. Expand Advanced, and click (Connection details) to open the Connection Details worksheet.

  3. Check your cable tray or conduit run to find out if you need to add more segments or change the elevation of other segments in order to reconnect the run.
  4. Optionally connect segments by adding transitions or bends and additional cable tray or conduit segments.

    Connecting cable tray segments at different elevations