Process Linework Dialog Box

The Process Linework command processes linework connectivity between points, using a specified linework code set in situations where a linework code set was not previously specified.

You can also reprocesses linework connectivity after you make corrections to the survey point descriptions in the Survey Point Properties Dialog Box.

Current Figure Prefix Database

Specify the figure prefix database.

Current Linework Code Set

Specify the linework code set.

Process Linework Sequence

Specifies the order in which survey point descriptions are processed to determine linework connectivity. Select one of the following:

  • By Import Order - processes points in the order in which they are imported. Point names are always processed by import order.
  • By Point Number - processes points sequentially by point number (ascending order only).
Insert Figure Objects

Inserts figures in the current drawing.

Insert Survey Points

Inserts survey points in the current drawing.