You can use the Demand Factor dialog to create and apply demand factor types.
Apply a constant demand factor
You can apply a constant demand factor to the loads regardless of their values. A constant demand factor is the default for any newly created demand factor, and the default calculation method if a demand factor is not specified for a load classification.
Apply a demand factor based on a total quantity
You can assign the demand factor to be based on the number of connected objects. For example, if there are two items, all loads are calculated at 100%. If there are ten items, then all loads are calculated at 65%.
The table displays the demand factor for each row of objects.
Apply a demand factor based on quantity ranges
You can assign the demand factor to be based on a percentage that varies as the quantity of objects increases. You can specify that the demand factors are calculated incrementally for different ranges.
For example, you can specify a demand factor for the largest 60 connected loads, and then specify another demand factor for the next 40 largest loads (61 to 100, etc.).
Each range represented by a row will be summed.
Assign a demand factor based on total load
You can assign a demand factor based on the total number of objects attached to a panel. Total load calculates the entire load at that demand factor.
For example, if the total load is under 100 VA the loads are calculated at a demand factor of 100%. If the total load is 300 VA, then the loads are calculated at 65%.
The table displays the demand factor for each row of loads.
Apply a demand factor based on ranges of loads
You can assign demand factors that are calculated incrementally for different ranges of loads.
For example, you can specify a demand factor of 50% for the range between 0 to 20,000 VA, and a demand factor of 25% for the range between 20,001 and 30,000 VA.
Each range represented by a row is summed.