You created a demolition plan but are not able to tag existing rooms.
Issue: Room elements only exist in the phase in which they were created; they do not persist across the phases of a project. A demolition plan typically shows existing elements from the previous phase and graphically alters the elements to be demolished. The existing rooms are from a previous phase, but they do not persist across phases, so they are not present in the demolition view and cannot be tagged.
Solution: Use 2 views overlaid to add rooms and tags to the demolition plan.
- Create an existing floor plan. Place rooms and tag rooms in the existing floor plan.
- Create a demolition floor plan. Use the Demolish tool and mark elements for demolition as required.
- Drag and drop the demolition plan from the Project Browser to place the view on a sheet.
- Create a duplicate of the existing floor plan using Duplicate with Detailing. Rename the view. (Example: Existing - Rooms Only)
- Select all elements in the duplicated view. Then use the filter to limit the selection to Rooms and Room Tags.
- Isolate the Rooms and Room Tags with the Temporary Hide/Isolate tool on the View Control Bar.
- Apply Hide/Isolate to the view from the Temporary Hide/Isolate tool on the View Control Bar.
- Drag and drop the Existing - Rooms Only view to the sheet where the demolition plan is placed.
- Change the view port type to omit a view title. You may need to duplicate an existing view port type and create a new one without the view title.
- Reposition the Existing - Rooms Only view to line up with the demolition plan. Use guides and snaps to aid in placement.