Use this workflow after you have exported a Autodesk Civil 3D model to Autodesk Storm and Sanitary Analysis.
| In Storm and Sanitary Analysis, double-click the Project Options node and set up required Project Options. See "Project Options" on page 175 of the Storm and Sanitary Analysis User's Guide. | 
 | 
| Set up rainfall options for the project (either an IDF Curve for Rational, or Rain Gage for other methods). | 
 | 
| Set up required Analysis Options See "Analysis Options" on page 69 of the Storm and Sanitary Analysis User's Guide. | 
 | 
| Refine subbasins | If you are using a TR-55 or TR-20 Hydrology Method, check the Subbasin Properties and set up the Curve Number for the soil groups for all subbasins. See "TCT TR-55 Curve Numbers" on page 347 of the Storm and Sanitary Analysis User's Guide. | 
| Refine inlets | You may need to adjust the Road & Channel Specifications and Gullies settings in the Inlets dialog box. 
 See "Inlets Dialog Box" on page 249 of the Storm and Sanitary Analysis User's Guide. | 
| Perform an analysis | Click the Run Analysis button. See "Performing an Analysis" on page 83 of the Storm and Sanitary Analysis User's Guide. | 
| Display analysis results | 
 | 
| Check the Subbasin Properties for each subbasin and review the peak runoff | The Peak Runoff is displayed in the Analysis Summary area of the Physical Properties tab. See "Analysis Summary Section" on page 345 of the Storm and Sanitary Analysis User's Guide. |