Use this procedure to add objects to an existing schedule table.
- Select the schedule.
- Click .
- In the drawing, select the objects to add to the schedule, and press Enter.
Use a window or a crossing window to select multiple objects. Objects that are already in the table are not added.
Note: You cannot add objects to a schedule table through RefEdit. Although the command appears to work during the RefEdit session, as soon as changes are saved back, the rows disappear from the schedule table. This is because you are actually selecting temporary copies of the objects in the file. In order to have objects that are in an xref or block display in a schedule table, select the xref. To include only selected objects from the xref or block, use a layer filter with the schedule table.