Add Equipment Load

For specific loads, such as a chiller or other equipment, you can define an Equipment Load.

To define an equipment load

  1. Click Analyze tab Electrical Analysis panel Equipment Load .

    The System Browser displays the Electrical Analytical Systems tab and an Equipment Load is created.

  2. Alternatively, press F9 to open the System Browser and from the drop-list, select the Electrical Analytical Systems tab if necessary. Click Add Equipment Load .
  3. In the Properties palette, specify the Load Classification, Voltage, Power Factor, and Apparent Load.
  4. In the System Browser, you can right-click an equipment load to view and modify its properties.

    You can schedule the Electrical Analytical Load to summarize both area-based loads and equipment loads. You can use standard schedule formatting capabilities to group and sum load totals.