Toposolid: Excavation Volume Parameters

Use the individual volume and total excavation information to know the exact amount of soil to be removed from the toposolid modeling.

Examples:

  1. Floor is a cutter element. In the Properties Palette Floors Dimensions, the Excavation Volume on Toposolid parameter refers to the portion that excavated on the Toposolid
  2. Mass cut (as cutter element) with Toposolid, Mass element will have the Excavation Volume on Toposolid parameter shows the portion of soil been taken out from the Toposolid.
  3. Toposolid as the Cuttee element.

    There will be two parameters:

    1. The individual Excavation Volume leading to the Dialog that shows all the cutter elements that booleaned with Toposolid.

    2. The Total Excavation Volume shows how much soil has been taken out of this Toposolid instance.

    You can also create schedules for those parameters:

    For Cuttee: Toposolid Total Excavate Schedule that has the Total Excavation Volume parameter.

    For Cutter: Excavate Multi-Category Schedule, and filter by the Excavation Volume.