When a change order is in the Work State, the Responsible Engineer can edit the routing, as well as view, add, and reply to comments. The Responsible Engineer can also withdraw a change order from the Work State and return it to the Open State.
In the main pane, right-click the change order and select View and Respond.
In the Change Order dialog box, select the General, Files, and Routing tabs to view basic information and attached files.
Select the Comments tab to view comments from other participants or to add your own.
Add comments:
Reply to comments:
Right-click a comment, and select Reply Comment.
In the Comments tab, click Add Comment.
Select the Comment tab and enter any comments.
To add an attachment, click Attachments and browse for a file in the vault or a file attached to the change order.
To markup a 2D .dwf file, use the Autodesk Composer markup tools shown in the graphics display. Click the help button on the Composer toolbar for help with using the Autodesk Composer tools.
Select the Email tab and modify the notification if appropriate.
Click OK to save the comment and send notification to all routing participants.
Status: To view the current status of the change order and review actions taken by the change order participants.
To review when the change order entered a particular state (including multiple times) and on what date, double-click a Status box.
Click Save and Close to save your comments.
In the main pane, right-click the change order and select Edit Routing.
In the edit routing dialog box, highlight a user on the left and click add.
To remove a user, highlight a user on the right, and click remove.
Click OK to save changes.
The change order returns to the Open state.
Upon a change order being submitted for Review, the change order enters the Review state.