Creating a Mass Floor Schedule

After creating mass floors, you can create a schedule for them. Use a mass floor schedule to assign usages or to analyze the design. If you change the shape of the mass, the mass floor schedule updates to reflect the changes.

To create a mass floor schedule

  1. Click Manage tabViews panelSchedules drop-down (Schedule/Quantities).
  2. In the New Schedule dialog, do the following:
    1. For Category, click Mass Floor.

      If Mass Floor does not display by default, select Show model categories in this view. For Filter list, select Architecture.

    2. For Name, specify the schedule name.
    3. Select Schedule building components.
    4. Click OK.
  3. In the Schedule Properties dialog, do the following:
    1. On the Fields tab, select the desired fields.

      See Selecting Fields for a Schedule.

    2. Use other tabs to specify filtering, sorting, and formatting of the schedule.

      See Specifying Schedule Properties.

    3. Click OK.

The schedule displays in the drawing area. If you included the Usage field in the schedule, you can assign a usage to each mass floor in the schedule.