Forecast Settings

Project administrators can access the settings for Cost Management from Services in Project Admin. This article focuses on the Forecast settings:

  1. Click Module Selector Module selector icon Arrow menu icon Project Admin option button.

  2. Select the Services tab.

  3. Select Cost Management in the left panel.

    Note: If you enter Project Admin directly from Cost Management, you start in this position.
  4. The General secondary tab is selected by default. Switch to the Forecast tab.

    Project Admin Services Cost Management General Settings showing Budget Fields configuration

Cash Flow

Here project administrators can set up forecast distribution for the cash flow in the Forecast tab.

First, choose between weekly and monthly distribution.

Note: This setting can't be changed after the forecast distribution is created on any budget.

Distribution Curves

This section allows administrators to select what to include in the cash flow distribution. There are several options related to both the Budget and Cost.

For the Budget:

For the Cost:

Distribution curves settings panel showing budget and cost options for cash flow forecasting

Note: Once any distribution item has been created, these settings cannot be changed.