RFIs Shared through Bridge Activity Log
The activity log for RFIs shared through Bridge provides a comprehensive summary of the RFI's journey across connected projects. This aligns with the standard RFI activity tracking but is optimized for cross-project visibility. While standard RFIs track every individual action, RFIs shared through Bridge create a consolidated summary of key events.
Key activities tracked in the source project include:
- Status changes
- Response submissions
- Official response selection
- Closure and distribution
A new activity type will be created in the receiving target projects - "RFI was shared from a project"
- This activity type acts as a summary of any important action that happened on the source project, and lists the involved users and times
- The user names and company name are text values, to act as a snapshot
Content
- Shared from Project (Account)
- Official Response
- Official Response Attachments
- A list of clickable links
- Official Response by (user) at (time)
- Coordinator / Manager that created the official response
- Question
- Closed by (user) at (time)
- Manager / Admin that closed the RFI
- Reopened by (user) at (time)
- Manager / Admin that reopened the RFI
- Responded by (user1, user2, user3, ... user10) at (time)
- The names of the Reviewers that provided the response(s)
- Moved to review by (user) at (time)
- Coordinator / Manager / Admin that moved the RFI to review
- Created by (user) at (time)