Import a Schedule

Import schedules from third-party tools to view, share, and collaborate on them in the Schedule tool. Supported formats include:

Note: The Schedule tool supports only XML Schema Version 20.12 for Primavera P6. XML schedules that use the calculated by longest part method show all activities as non-critical.

Only Project Administrators or members with Manage or Create permission in the Schedule tool can import a new schedule.

Important: Deleting the Schedule tool files folder deletes all schedules.

To import a schedule:

  1. Open the Schedule tool.
  2. Click Import schedule.
  3. Select the file to import.

The schedule can take a few moments to upload and process. You'll receive an email notification when it's ready. When processing finishes, the schedule opens in the Gantt view within the Schedule tool.

The imported schedule appears in the Schedule tool, while the Files tool stores the imported file. Forma Build creates a Schedule tool files folder in Project Files, and names the folder after the imported file. Moving or renaming the folder doesn't affect the connection between the Schedule tool and the stored file.

Forma Build keeps permissions for the Files subfolder that contains the schedule in sync with the schedule permissions. People without access to the schedule in the Schedule tool can't download the source file from the Files tool.

The Schedule tool supports multiple schedules. To import multiple schedules:

  1. Click Import.
  2. Select the schedule file to import.

Forma Build creates a Files tool folder for each imported file.

This table shows the supported types of data for each file format. Missing information, whether not supported or not specified, appears as "unspecified".

Important: Importing XER files can cause issues with non-English characters. Use XML files when possible.
Primavera P6 Microsoft Project Asta Powerproject
XER XML MPP XML PP
Activity ID Supported Supported N/A N/A Supported
Start date Supported Supported Supported Supported Supported
Finish date Supported Supported Supported Supported Supported
Duration % complete Supported Supported Supported Supported Supported
Labor resources Supported Supported Supported Supported Supported
Duration Supported At completion Supported At completion Supported Supported Supported
Predecessor Supported Supported Supported Supported Supported
Successor Supported Supported Supported Supported Supported
Planned start/finish Supported Supported Supported Supported N/A
Actual start/finish Supported Supported Supported Supported Supported
Baseline start/finish N/A Supported Supported Supported N/A
Activity codes and outline codes Supported Supported Supported Supported Supported
Data date and status date Supported Supported Supported Supported Supported