Process submittal items to move them through review and approval, see who needs to act next, and close them when review is complete. Each submittal item goes through review and approval stages that you track in the workflow table and workflow bar.
See where an item stands
Each item shows its current stage in the review process.
In review status, the workflow bar shows Pending review from instead of Reviewers to show who still needs to take action.
The workflow bar shows Responded: X to show how many reviewers have already responded in the current review step.
Hover over Pending review from to see who hasn't responded yet. Hover over Responded to see who has completed their review.
User avatars in the workflow bar represent people who still need to provide their review rather than all reviewers.
The general information shows basic details about the submittal item, such as description, type, and spec section.
Track the review
The workflow table summarizes the workflow with important dates, attachments, and comments.
In review steps that are in progress or completed, the table lists reviewers who have already responded first, in the order of their response.
Use the response and action column to act on the submittal item, such as approving it or requesting revisions.
Select a Review template or edit the review workflow for the submittal item.
Add up to 30 required reviewers and 20 optional reviewers to each review step. A workflow can have up to 6 steps.
Plan around required dates
The planning dates help you plan and schedule:
Required date
Required approval date
Required on job site date
Lead time
Discuss and link related work
Review the history of all activity related to the submittal item.
Comment and @mention others to collaborate.
Link the submittal item to other project elements, such as Assets, Files, Forms, Issues, PCOs, Photos, RFIs, other Submittals, Schedule, and Sheets. References keep the submittal aligned with other project components.
Add references to Submittals on mobile
Add references to Submittals directly from the Forma app.
Open any tool other than Submittals.
Tap Add reference where all references are listed.
Select the Submittal item you want to link.
Tap Save.
References you add on mobile sync immediately with the web application, so all team members have access to complete submittal information.
See who still needs to act
The Submittals list view includes a Pending action from column after the Ball in court column. The column shows reviewers who haven't yet provided their review in the current review step.
Pending action from shows the same value as Ball in court when an item isn't in review status.
Pending action from follows the same display format as Ball in court:
Shows assigned users, roles, or companies who still need to review the item.
Highlights the current user if they need to act.
Displays +X more when multiple reviewers are pending.
Shows the complete list of reviewers on hover.
Close, revise, or void a submittal item
Close and distribute
Click Close and distribute to conclude the review of a submittal item. The system distributes the submittal information to all individuals involved in the process. Closing shows that reviewers have reviewed the submittal and provided the necessary feedback or approval.
You can share Closed submittals to the Files tool. Once in Files, you can share the submittals to another Autodesk Forma project using Bridge and manage the shared items in the Bridge tool.
Create a new revision
Click Create new revision to create a new version of the submittal item. When you create a new revision, you can:
Assign a Responsible Contractor.
Set a due date for the submitter.
Add watchers who need to be informed or monitor the submittal.
Important: Submittal Managers and Project Administrators can create new revisions or close submittals regardless of their status, except for items marked as Draft or Void.
Step back to the responsible contractor
You can step back an item in Open status to the Responsible Contractor. This lets you correct an item you created in Open Submitted status. The step back is recorded in the activity log as a standard entry.
If an attachment upload fails when you create an item, the item still exists. Step it back to the Responsible Contractor, and submit it again.
Void a submittal item
Click Void to invalidate a submittal item that's no longer relevant or necessary for the project. Don't consider a voided submittal item in ongoing project activities.
Assign roles and companies
Assign roles and companies as Submittal Managers, Responsible Contractors, and Reviewers to simplify your submittal workflows. You can assign entire roles or companies to review submittals, rather than individual users.
You can assign roles and companies as Submittal Managers, Responsible Contractors, and Reviewers in the following situations:
When creating a submittal.
In custom review templates.
In Review Builder.
In item details.
To assign roles and companies as reviewers:
Open the submittal item.
In the Manager, Reviewers, or Responsible Contractor fields, open the list. The list has separate sections for Members, Roles, and Companies.
Select the role or company you want to assign.
Note: Don't select individual users who belong to that role or company.
Click Done to save the changes.
After you assign a role or company:
All users in that role or company receive email notifications about the review assignment.
The system handles permissions automatically. Users in the role or company gain access, and lose access if you remove them from it.
For bulk actions, use the role or company name when assigning multiple items.
You can assign role and company names in review templates and workflows.
The role or company name displays in relevant columns on the items list and details pages.
In the workflow table, role names show the actual users who performed reviews.