EPS Simulation

The Simulation Time feature of InfoWater Pro allows you to change the timestep at which an extended period simulation will be analyzed. If you select the Steady State checkbox, then only a steady-state model will be analyzed. A simulation time option can be set up for each unique scenario within InfoWater Pro.

An extended period simulation (EPS) is any modeling run that evaluates system hydraulics for a duration greater than a single hydraulic timestep (steady state). You are provided with many tools in InfoWater Pro that allow customization of an EPS simulation.

Many features of InfoWater Pro including SCADA, Energy Management, Water Quality, and Logic Rules are dependent upon a model being analyzed over a series of timesteps (Extended Period Simulation).

To create a new Simulation Time settings, select the Operations Tab from the Control Center and select Simulation Time. Right click and select New and supply a unique name and description for the simulation time options. The following dialog box will appear:

Simulation Time Options

When performing an EPS, many modeling parameters are dependent on analysis timesteps (intervals) and duration. The following durations and time steps may be specified:

Once a simulation time is created, it can be associated with any scenario that you specified or evaluated at any time via selection from the Run Manager.