Manage an activity's lifecycle

Note:

For users with Fusion connected sites, references to the 'Items' workspace should be the 'Components' workspace.

Every engineering project activity comes with the following default workflow. It is found in the Workflow tab of the activity. The workflow is the same for both milestones and activities.

activity workflow

Request work begins on the activity

At the beginning of a project, all milestones and activities are in the Planning state. To begin working on an activity, you must submit it as part of its parent milestone activity. You cannot submit individual activities.

A milestone and its activities may be moved to the Requested state in one of several ways:

The milestone and its activities are moved to the Requested state. An email is sent to all members of the team chosen to work on that milestone. The activities also appear in their My Outstanding Work section of their dashboard.

From here there are three options:

Claim an activity

When an activity is assigned to a team, everyone in that team is notified when the activity is requested and it appears on each team member's dashboard. However, only one person can claim the activity.

To claim an activity, click the Accept transition to move the activity to the In Work state. This means your name is added to the Assignee field and it is removed from all other team members’ main dashboards.

Work on an activity

As you’re completing an activity, you should update the activity to indicate the progress you've made.

Update the progress of the activity

Now that the activity is in the In Work state, you may select from a number of percentage values to represent the completion level of the activity. This can be helpful for the project manager to ensure progress is being made on the project overall.

To update the progress of the activity:

  1. Open the activity.
  2. From the Workflow actions drop-down list, select the percentage level that you feel accurately describes the completion level of the activity.
  3. Optionally, enter a comment, then click Confirm.

activity progress

For the activity as shown on the Gantt chart, part of the bar representing the activity length is darker to visually indicate how much progress has been made on the activity. The progress bar on the activity is also updated with the value that you chose.

Activity effort

As you work on the activity, you should log the number of hours you have spent on it in the Effort tab.

activity effort

This total number of hours for the activity is rolled up and is shown in the Others section in the Project Activity tab of the activity once the activity has been completed. The total effort across all activities in the project is shown on the engineering project in the KPIs section in the Engineering Project tab on the engineering project.

From here, there are three options:

Complete an activity

An activity may be completed from the Requested, In Work, and Review states. This is to enable flexibility in how and when you mark an activity as complete.

From the Workflow tab, click the relevant Finish transition to complete the activity.