Before running the Title Block Update, enter the project description lines and drawing values that are mapped to attributes on the title block.
-
Click
. Find
The Update Title Block dialog box displays.
- Select the values to update on the title block, along with SHEET and SHEETMAX if new drawings were added to your project. Note: If you want to save these selections, click Save. The settings are stored in the default.wdu file.
- (Optional) Select Resequence sheet %S value.
Renumbers the sheet values and changes the sheet max value. It is commonly used when drawings are added to the project drawing set.
- (Optional) Select Activate each drawing to process. Note: This option is necessary if there are user-defined values mapped to the title block that require activating the drawing to retrieve the values.
- Click OK Project-Wide.
- Select the drawings to process and click OK.
Note: You can also select the drawings or folders in Project Manager, right-click and select Title Block Update. Selected drawings are preselected in the Select Drawings to Process dialog box.