When you set a task to incomplete, you need to assign a root cause.
You can also reschedule the completion date and add a note.
Using the Edit Activity Dialog
- Click List View
or Gantt View
. Then in the view, for an activity, click Edit
.
- In the Edit Activity dialog, for Status, select Incomplete.
- Select a root cause for the inability to complete the task. Root causes are defined by project admins.
- Select Reschedule This Activity. By default, this adds a day and reschedules the finish date. Change the Delay and new Finish Date as needed.
- (Optional) Add a note.
- Click Save As Incomplete.
Using the Edit Status Buttons
- Click List View
or Gantt View
.
- Select one or more activities. Status buttons appear in the action bar.
- Click the Incomplete button.