Share
 
 

To Synchronize Individual Display Settings With AEC Standards

Use this procedure to synchronize display settings in a project drawing with the project standards.

Note: Display settings should always be synchronized with the latest standard settings. Out-of-synch display settings in a project can cause objects to be displayed inconsistently.
  1. Open a project drawing.
  2. Click Manage tabStyle & Display panelDisplay Manager.
  3. In the Display Manager tree, navigate to the display setting you want to synchronize.

    You can synchronize the following items:

    • display configurations
    • display sets
    • display representations
  4. Select the item in the tree, right-click, and select Synchronize with Project Standards.
  5. In the Synchronize Drawing with Project Standards dialog box, select the items to synchronize.
  6. Click OK to start the synchronization process.

Was this information helpful?