The VegetatedSwale subassembly creates a vegetated swale to treat storm water.
Attachment
The attachment point is at the middle top of the vegetated swale.
Input Parameters
Parameter |
Description |
Type |
Default |
---|---|---|---|
Side | Specifies which side to place the subassembly | Left / Right | Right |
Bottom Width | Swale bottom width | Numeric, positive | 3 |
Include Amended Soil | Include amended soil under swale | Yes / No | Yes |
Daylight Slope | Daylight slope | Numeric, positive | 2 ( : 1 ) |
Amended Soil Depth | Depth of amended soil | Numeric, positive |
0.5 ft 0.15 m |
Underdrain Diameter | Diameter of underdrain | Numeric, positive |
0.5 ft 0.15 m |
Underdrain Depth | Depth of underdrain | Numeric, positive |
1 ft 0.30 m |
Underdrain Width | Width of underdrain | Numeric, positive |
1 ft 0.30 m |
Include underdrain | Include underdrain | Yes / No | Yes |
Swale Depth | Depth of swale | Numeric, positive |
1 ft 0.30 m |
Side Slope Left | Left side slope | Numeric, positive | 4 ( : 1 ) |
Side Slope Right | Right side slope | Numeric, positive | 2 ( : 1 ) |
Target Parameters
This section lists the parameters in this subassembly that can be mapped to one or more target objects. For more information, see To Specify Corridor Targets.
Parameter |
Description |
Status |
---|---|---|
Surface Target | Name of the daylighting surface. The following object types can be used as targets for specifying the surface: surfaces. | Optional |
Runtime Logical Assignments
None.
Output Parameters
None.
Behavior
Starting at the attachment point, the swale is built using the input parameters. If the surface target is set, the daylight surface is found (only for cut situations). If include underdrain is set to Yes, then the underdrain is built.
Layout Mode Operation
In layout mode, the vegetated swale is built.
Point, Link, and Shape Codes
The following table lists the point, link, and shape codes for this subassembly that have codes assigned to them. Point, link, or shape codes for this subassembly that do not have codes assigned are not included in this table.
Point, Link, or Shape |
Code |
Description |
---|---|---|
P1 | Flowline | Flowline of the vegetated swale |
P2, P3 | Swale | Edge of swale |
P4, P5 | Hinge | |
P6, P7 | Daylight, Daylight_Cut | |
P10-P13 | Underdrain | |
P14 | Pipe_Invert | Invert of underdrain pipe |
L1-L4 | Swale, Top | Top of swale |
L5, L6 | Daylight, Daylight_Cut | |
L9 | AmendedSoil, Datum | Bottom of amended soil |
L14 | Underdrain, Datum | Bottom of underdrain |
S1 | AmendedSoil | |
S2 | Underdrain |
Coding Diagram