Follow these steps for each new Autodesk Vault project.
|
Designate a Vault server and database for the project. | |
![]() |
||
|
Create the project folder and subfolders, ideally using a standard template. | |
![]() |
||
|
Set appropriate access permissions for user groups to protect the project data. | |
![]() |
||
|
Identify project objects and develop a strategy for partitioning project object data. | |
![]() |
||
|
While adding source drawings to the project, designate which objects can be shared with other drawings. | |
![]() |
||
|
Create read-only object references to save space in the consumer drawings. | |
![]() |
||
|
Ensure that data references are regularly updated with the latest versions of project objects as designs change. | |
![]() |
||
![]() |
When a major milestone is reached, use the Vault Labeling feature to tag the appropriate version of each project file. | |