Share

Synchronizing Drawing Data with Project Data

Product Documentation
Intermediate

You can update an open drawing with the latest versions of all project objects and point data.

The Sync To Project command updates out-of-date drawings that reference project objects. It also updates any out-of-date project points contained in the drawing. The out-of-date condition can occur when someone checks in a project object’s source drawing or checks in project points.

Local copies of out-of-date source drawings and project points are replaced with the latest version from the project database.

To synchronize a drawing

  1. In Toolspace, on the Prospector tab, under the Open Drawings collection, right-click the drawing you want to synchronize.
  2. Click Sync To Project.
  3. In the Sync To Project dialog box, select the out-of-date project objects you want synchronized.
  4. Click OK.

Toolspace Context Menu

Prospector tab: Open Drawings collection right-click <drawing name> Sync to Project

Dialog Box


Was this information helpful?